State Grid Changzhou renovates smart grid

  • August 19, 2026
  • Esther Shein

China’s State Grid Changzhou Power Supply Company recently announced that it has completed an automated upgrade of pole-mounted switches on the 10kV Huangjia Line. The utility–the largest in the world–said it has rolled out a refined zero-perception construction model to ensure reliable power supply amid the peak summer electricity demand.

The project benefited over 400 households in Huangjiayuan Community in the Jintan District with nearly uninterrupted power service throughout the renovation, according to the company. Officials added that this creates a replicable benchmark for grid optimization and customer-centric power upgrades.

Developed years ago, the Huangjiayuan Community faces mounting power supply challenges as annual summer electricity consumption continues to surge. A hidden hazard is aging pole-mounted switch equipment on the 10kV line because it restricts local power supply stability. To address the pain point fundamentally, State Grid Changzhou said it upgraded the outdated devices to intelligent automated switches equipped with real-time fault detection and rapid isolation functions. The newly operational smart switches can instantly identify line faults and drastically cut power outage duration, significantly elevating the overall reliability of regional power grid operation, according to State Grid Changzhou.

The company adopted a tailored construction strategy featuring pre-power generation, live-line coordination and phased operation in order to eliminate construction disruptions to residents’ daily lives. A total of eight low-voltage generator vehicles were deployed for collaborative power guarantee, while professional live-line operation teams disconnected high-voltage side leads without cutting off the main trunk line power supply.

Thanks to the refined and tech-enabled construction scheme, only a handful of residents experienced a very brief power switching process, and the vast majority of end users remained unaware of the ongoing grid renovation, according to the company.

Since the start of 2026, State Grid Changzhou has aggressively promoted zero-perception grid construction across its service areas. For example, in the Jintan District alone, the company said it has completed more than 4,500 live-line power operations and generator-assisted construction projects in the first half of the year, effectively minimizing power outages and steadily improving regional power supply quality.

During the critical peak summer power consumption period, the intelligent switch upgrade has further consolidated the grid’s operational stability. Moving forward, State Grid Changzhou said it will continue to optimize construction methodologies and refine service standards. By prioritizing uninterrupted power operation in all grid upgrade and renovation projects, the company will normalize the service philosophy of No power interruption equals optimal service,” with the goal of delivering consistent, reliable and people-centric power protection for local households and industrial users.